Completed projects

Completed Projects
For the last 30 years, we have been providing solutions for the large-scale energy generation and industry in the key sectors of the economy. Our portfolio includes dozens of completed projects, both in Poland and abroad. We provide services in the field of overhauls, modernisation and production of heating and industrial systems. We perform diagnostics, prepare survey reports, and carry out advanced material testing. We have the know-how and experience, which allow us to successfully complete the most demanding projects.
Location of work The scope and location of the performed work
SODA Polska Ciech – EC Janikowo • Carrying out mechanical works, related to the transferring of the TP6/6 (6 MW) turbine set from the Alwernia Chemical Plant, and installing at Janikowo CHP Plant – the job was ordered by INWAT Łódź
• Modernisation of OP-110 boilers No. 1 and 3 at ZP Inowrocław
• Carrying out mechanical works, related to after-failure repairing of the TG-1 turbine set at Janikowo CHP Plant (7MW) – the job was ordered by INWAT Łódź
• Repairing of the TP-6 turbine set and Lang 20.5 MW TP-5 turbine set, at Janikowo CHP Plant
• Diagnostic tests: CKTI-75 boiler drum No. K1, OP-140 boiler drum, OP-140 boiler chambers
• Non-destructive testing of welded joints – repairing of K1 and K5 boilers
KGHM Polska Miedź S.A.
Copper Works in Głogów
Installation of a 7.4MW pass-out and condensing turbine set, including auxiliary equipment and pipelines, in the system – the job was ordered by INWAT Łódź
Grupa Azoty S.A. in Tarnów Installation of a 21MW pass-out and condensing turbine set, including auxiliary equipment and pipelines, in the system – the job was ordered by INWAT Łódź
• Delivery and assembly of pipelines and equipment, as part of the erection of the Polyamide Plant II 80 tt/year located within Grupa Azoty S.A. in Tarnów
• Overhaul of TPG 170 No. 1 steam boiler – mechanical industry, at Centrum Energetyki GA S.A.
• Major overhaul of the Lang 4 turbine set, at Centrum Energetyki GA S.A.
• Major overhaul and modernisation of the WPT-25-3 and LANG 24.1MW turbine sets together with auxiliary equipment – the job was ordered by INWAT Łódź
• Manufacture, delivery, and assembly of pressure elements of the 2nd duct of the K5 boiler, as part of the objective “Construction of a flue gas denitration system at the ECII CHP Plant”
• Major overhaul of the OP 230 No. 5 steam boiler, at Centrum Energetyki – the mechanical part
Grupa Azoty
“SIARKOPOL” S.A. Mines and
Sulphur Chemical Plant
• Overhaul of the 2RB1 SUWZ reactor at the “Osiek” Sulphur Mine
• Installation and start-up of a new drying node on the insoluble sulphur system
• Delivery and assembly of pipelines and fittings, as well as delivery and assembly of steel structures related to the project “Modernisation of production by installing a New System for Sulphur Insoluble in Carbon Disulphide”.
• Installation of E7709 A and B condensers, together with piping, within the premises of KiZChS “Siarkopol” Chemical Plant in Dobrów
• Installation of A1107, A1111, and A1120 tanks, together with piping, within the premises of KiZChS “Siarkopol” Chemical Plant in Dobrów
• Non-destructive tests carried out during the construction of pipelines for new systems, at Siarkopol Grzybów
IP Kwidzyn Sp. z o.o. • Repairing of the bark boiler and boiler’s auxiliary accessories, together with performing tests for a supervision pressure test
• Diagnostic tests: OP-140 KW-2 type steam boiler drum; CKTI-75 boiler drum No. K1
TAURON Jaworzno Power Plant Installation of pipelines accompanying the J910 turbine set – the job was ordered by Doosan Babcock Energy Rybnik
PGNiG Termika SA Warsaw • Modernisation of the corners of WP-200 boiler No. K-4, at Kawęczyn CHP Plant
• Repairing OP-430 K-10 and K-15 boilers, at Siekierki CHP Plant in Warsaw
• Major overhaul of the Tz-8 turbine set, at Siekierki CHP Plant
• Overhaul of the Tz-1 turbine set, at Żerań CHP Plant
• Major overhaul of the 13P110 (110 MW) -Tz-10, Tz-7 turbine sets, at Siekierki CHP Plant
• Overhaul of water management equipment, at Żerań CHP Plant
• Overhaul of the 13P110 Tz-5 and Tz-6 turbine sets, at Siekierki CHP Plant
• Performing temporary and emergency mechanical works on turbine sets, auxiliary equipment in the plant room, boilers, and auxiliary equipment for boilers installed at PGNiG TERMIKA SA, under the framework agreements
PGE Dolna Odra Power Plant • Reconstruction of the pressure system of Benson A and B boilers, at the Pomorzany CHP Plant
• Testing and evaluating the technical condition of the pressure elements of boiler No. 8
• Framework agreement for “Repairing of boilers and auxiliary equipment at the Dolna Odra Power Plant” – the pressure part and high pressure pipelines
• Overhaul of the OP-650 boiler of power unit No. 6, including high pressure pipelines
• Medium-scale extended repair of the boiler’s pressure part and high pressure pipelines of power unit No. 7 – the job was ordered by ZEC SERVICE Wrocław
• Performing modernisation works, regarding the incineration system of OP 650 boiler No. 8, at the Dolna Odra Power Plant, in order to reduce NOx emissions – the job was ordered by Energotechnika-Energorozruch S.A. Gliwice
• Major overhaul of the Lang 4 turbine set, at Centrum Energetyki of Grupa Azoty S.A.
TAMEH Polska Sp. z o.o.
Production Plant in Kraków
• Installation of a complete SIEMENS SST600 55MW steam turbine set, together with auxiliary equipment – the job was ordered by BUDIMEX S.A. Warsaw
• Delivery and assembly of the pipelines and equipment, as part of the installation of the SIEMENS SST600 55MW steam turbine set – the job was ordered by BUDIMEX S.A. Warsaw
• Prefabrication and assembly of complete pipelines, together with the associated fittings and accessories for KH5, KH6 boilers – the job was ordered by Control Process Kraków
• Production and delivery of assembly segments of steel pipelines, as part of an investment task. Reconstruction of the cooling water system at TAMEH ZW Kraków – the job was ordered by UNISERV S.A. Katowice
Polenergia Elektrociepłownia Nowa
Sarzyna Sp. z o.o.
Major overhaul of a steam turbine set type DK125/400RA1Z1E1
Mondi Świecie S.A. • Shutdown repair work at a department of the Mondi CHP Plant – Scheduled standstill of the plant in the years 2017 and 2019
• Overhaul of turbine set No. 2
• Diagnostic tests of the pressure part of the BFB boiler
ENERGA
Ostrołęka S.A. Power Plant
Modernisation of the high- and medium-pressure parts of the 13K200 TG-2 turbine – the job was ordered by Siemens Warsaw
• Delivery of F35-030 clutch fluid coolers, F12-010 lubricating oil coolers, F15-10 sealing oil coolers, F60 lubricating oil coolers
PGE CHP Plant Kraków • Major overhaul of boiler type OP-380 No. 1
• Major overhaul of boiler OP-430 No. 4 – the job was ordered by BETA Ostrołęka
• Evaluation of the technical condition of the fresh and secondary steam pipelines of the K1 boiler, at the CHP Plant in Kraków
• Diagnostic tests of the OP-380 boiler drum, station number K1
• Diagnostic tests, evaluation of the technical condition, and the possibilities and conditions for further safe operation on the OP-380 and OP-430 boilers
PGE GiEK CHP Plant in Turów Installation of the turbine pipelines during the construction of a new 496MW power unit – the job was ordered by ZRE Katowice (Repair Plant)
PETROPLUS PETIT COURONNE Oil
Refinery
Overhaul of the reactor in the refinery – the job was ordered by Foure-Lagadec
EDF POWER PLANT
Le Havre
Replacement of a secondary steam high temperature superheater on one of the boilers – the job was ordered by Alstom Power Service France
NORMANDIE OF TOTAL Refinery HARFLEUR Overhaul and installation of equipment on production systems – the job was ordered by Foure-Lagadec
EDF POWER PLANT
Le Havre
Replacement of screen elements, replacement of sealing boxes on superheaters, including flow-through pipes going through the screens – the job was ordered by Alstom Power Service France
EDF POWER PLANT CORDEMAIS Replacement of sealing boxes on low and medium temperature primary steam superheaters, including flow-through pipes going through the screens. Replacement of screen panels with bent sections for hatches and inspection openings – the job was ordered by Alstom Power Service France
GDF SUEZ (Engie) Cofely West Industrie
BV Dordfrecht
The Netherlands
Prefabrication of pipeline modules – Dordrecht – The Netherlands
EDF POWER PLANT CORDEMAIS Replacement of screen sections, replacement of bent pipes intended for hatches and inspection openings, replacement of sealing boxes of the primary steam superheater, including flow-through pipes going through the screens. Installation of components in the absorber’s flue gas desulfurisation system – the job was ordered by Alstom Power Service France
Arcelor Mittal Fos-sur-Mer Replacement of all screens, including piping, on one of the boilers – the job was ordered by CNIM
Suez Novalie Avignon Waste Incineration
Plant
Replacement of the pressure elements (screens, superheaters) on the boiler of the waste incineration plant – the job wasordered by CNIM
Arcelor Mittal Fos-sur-Mer Replacement of all screens, including piping, on one of the boilers – the job was ordered by CNIM
EDF POWER PLANT CORDEMAIS Replacement of screen sections, replacement of bent pipes intended for hatches and inspection openings, replacement
of sealing boxes of the primary steam superheater, including flow-through pipes going through the screens. Installation of
components in the absorber’s flue gas desulfurisation system – the job was ordered by Alstom Power Service France
Arcelor Mittal Fos-sur-Mer Replacement of all screens, including piping, on one of the boilers – the job was ordered by CNIM
UTVE Lyon Sud Waste Incineration Plant Replacement of the pressure elements (screens, superheaters) on the boiler of the waste incineration plant – the job was ordered by CNIM
Suez Novalie Avignon Waste Incineration
Plant
Replacement of coils on the coal boiler’s primary steam superheaters – the job was ordered by CNIM
Arcelor Mittal Fos-sur-Mer Replacement of hanger tubes, coils of superheaters, screen pipes, and other repair work carried out on the boiler in the waste incineration plant – the job was ordered by CNIM
SNVE Waste Incineration Plant in Grand-Quevilly, France Replacement of screens on the boiler of the waste incineration plant – the job was ordered by STMR
See projects,
hovering over the point
Click on the point
and see the project